Mexus Gold US announced that on April 12th the company plans on blasting at its Santa Elena mine located near Caborca, MX. The blast will produce approximately 10,000 tons of mineralized material averaging 2.2 gpt Au. Mexus expects to be producing gold from this material within 30 days of the blast. The company continues to speak to multiple mining companies concerning partnerships for all its properties. The company [...]
Mexus Gold US is pleased to announce that it has received the necessary explosives permit which will allow the company to move forward with mining of the company's high grade Mexus II and Julio vein structures. As previously noted, these areas contain up to 16 gpt Au with an average of 4.2 gpt Au. With drilling already completed at the Mexus II area the company expects to perform the first blast within the next week. This [...]
Mexus Gold US announced that it continues to be approached by multiple mining companies. These companies are interested in a drill with option to purchase agreement based on their proven 43-101 results or a joint venture production partnership. All of Mexus' properties are currently being reviewed. These include the Santa Elena mine which is currently in limited production, the Mabel gold/copper property which shows [...]
Mexus Gold US announced that it continues to mine the Mexus III pit area at its Santa Elena mine. The increase in mining efforts comes after a 20 day slow down due to a COVID outbreak of some of its mine employees. The crew is now COVID free with the company taking extra measures to ensure the safety of all involved. Mexus CEO Paul Thompson recently received a vaccination shot adding confidence when traveling to the mine [...]
Mexus Gold US announced that it continues to work the Mexus III area at its Santa Elena mine producing a detachment structure mineral with abundant sericite and oxide filled boxwork averaging 1.02 g/t Au. There are areas with higher grade zones where the silica content is noted often with visible gold. Argonauts 2015 limited drilling program intercepted this zone from 32 to 45 meters in depth with an average grade of 1.05 [...]
Mexus Gold US announced it is on schedule to meet its goal of reaching 100 gpm to the heap leach pad by February 1st. The mine, located in Caborca, Sonora State, Mx, continues to expand production. Mexus geologist, Cesar Lemas, provided details on the build out and production ramp up: “Mexus continues mining at the Mexus III area where a potent shear zone is being followed. Assayed results are showing between .7 to 1.3 [...]
Mexus Gold US released an update on mining operations at its Santa Elena mine located in Caborca, Sonora State, MX. Over the past few months the company has replaced the original heap leach pad and added mineralized material from the Mexus III pit. This area has an impressive geological structure as a mixed oxide thrust shear zone with shattered quartz fragments and some quartz stock work near the major quartz vein. An [...]
Mexus Gold US announced that on Monday, December 21st, the company will sell its initial production of gold from recent efforts at its Santa Elena mine located in Caborca, MX. This initial sell is on time and will meet the company’s initial goals for implementation of its mining plan. Mexus expects production and sales to increase every two weeks moving forward with additional confirmations to follow. About Mexus Gold US [...]
Mexus Gold US announced that on 12/12 the company produced gold concentrate from the new heap leach pad at its Santa Elena mine located in Caborca, MX. The concentrate was moved to a secure site for smelting. The resulting gold dore will be sold to the company’s U.S. buyer by 12/22. The production is confirmation that the new heap leach pad is producing as expected. “The outlook for 2021 is extremely positive as we expect [...]
Mexus Gold US announced that the sale of gold from production at its Santa Elena mine located near Caborca, MX is expected to occur by December 31st. This sale will represent the first 15 days of production from the company’s newly completed heap leach pad. In addition, Mexus continues to blast hole drill on both vein #2 and the Julio vein at the mine site which coincides with a build out of a drill program guiding [...]
Mexus Gold US is pleased to announce that leaching has commenced on its recently completed 250,000 ton leach pad. Leaching of vein 2 mineralized material is under way and returning values of .32 to .42 gpt Au in solution. Flows are expected to reach .6 gpt Au in solution by December 16th. Future production drilling on vein 2 and the Julio quartz vein continues. Mexus CEO Paul Thomspon Sr. added that gold production by [...]
Mexus Gold US announced that it has completed phase 1 of its new heap leach pad. The 250,000 ton pad, which is expandable to 1,000,000 tons, will have crushed mineralized material placed beginning 11/17. This material, averaging 2.7 Gpt Au, should begin leaching by 11/21. The company is looking for a return of .6 Gpt Au in solution. Start up flow at 10.5 liters per second is expected to return approximately 17.5 oz Au per [...]